What happens here

Given the lack of easy access (only through a window) and the significant volume of concrete required (over 10 cubic yards, versus a typical 1-3 yards for similar jobs), a concrete pumper is utilized. This specialized machine pumps pre-mixed concrete through a large hose, delivering it directly into the basement trenches. This method is praised for its efficiency, reduced mess (compared to mixing hundreds of bags of concrete by hand), and ensuring a consistent mixture that cures uniformly, preventing cracks.

Goal: Efficiently and cleanly fill excavated trenches with concrete.

Tools and materials

  • Large Concrete Hose — Transporting concrete from the pumper into the basement
  • Trowel/Shovel — Spreading and leveling the freshly poured concrete
  • Plastic Sheeting — Separating the drainage system from the fresh concrete
  • Pre-mixed Concrete — Filling the excavated trenches

What they say

Hide

two cubic yards of concrete on average going in we'd hand mix that in place right down in the basement on this job we have over 10 yards of con that has to go in and it has to be snaked down and through the basement which really doesn't have not only no no easy access points but has no ventilation so what we're opting to do with this job is use a concrete Placer and have a mixing truck already bring in premixed concrete and we're going to actually use a hose to bring it right down into the customer's house why is this important is because we're going to save a lot of time doing it this way we're going to save a lot of mess for the customer because we're able to get in and get the concrete pour very quickly if we brought it in with bags and we mixed it ourselves we'd have to bring in hundreds and hundreds of bags of concrete carry them down into the basement bring a mixer in and then bucket that material down into the basement it would get really messy really fast this is the quick way it gets the job done and it actually saves uh um overall expense on the project for both the customer and for us here you can see the only access point into the basement is through this window without coming through the entire house so this is the hose that's actually pumping the concrete into place to fill up these trenches you can see some of the concrete going in and there's the hose and that's how we're getting the concrete into this job so that we're not uh creating a huge mess for this customer so this entire room was void of footings and actually this is a pillar right here that holds up a good portion of the house and that had nothing underneath it so we were actually uh dug down around that footing and put extra Concrete in removed more material so that's part of where some of the ex so here you can see how we get the concrete in place it's quick easy easy in comparison to bringing in bags of concrete hand mixing it and trying to get it Pour and the the key component to doing it this way is the consistency all of the concrete is wet at the same time and it all dries at the same time that's huge to make sure that you don't get any differential cracks and settlement in the creek as it's being process this is all just getting so what you heard him just say was that that entire area gets fill build in and I was talking about the differential drying between the materials when you have dry concrete and you put wet concrete next to it you get a crack that's not cohesive and…