Compact Backfill and Geogrid Layers

0:09
19:47
462.8K views

At 0:09 in

How To Build an Engineered Retaining wall & Avoid Contractors that cut corners

What happens here

After placing each layer of geogrid, cover it with structural fill (e.g., clean, angular aggregate or well-graded soil) in uniform lifts (typically 4-6 inches). Use a heavy-duty plate compactor (like a 1000-pound plate compactor) to achieve maximum compaction of the structural fill, both directly on the lift and in the transition zones (areas where the excavation tapers). Even areas that are difficult to access should be compacted. This process ensures that the soil mass acts as a cohesive unit with the geogrid, preventing settlement and maintaining the wall's stability. During periods of rain or when work stops, cover exposed compacted areas with tarps to protect them from erosion and maintain compaction.

Goal: Thoroughly compact each lift of structural fill and geogrid to achieve the required density and prevent future settlement.

Tools and materials

  • Plate Compactor (e.g
  • 1000lb)
  • Structural Fill Material
  • Tarps

What they say

Hide

[Music] This is the perfect cross-section of a retaining wall. You can see where all the drainage aggregate is and then you can see where the structural fill soil

Auto-generated from the video audio.