What happens here

After paver removal, the crew prepares the sub-base for the new patio. This involves using Class 5 aggregate (a mix of 3/4 inch rock with fines). The narrator explains the difference between natural Class 5 and recycled Class 5 (used here), noting that recycled Class 5 compacts to a concrete-like hardness, providing a solid foundation, but is harder to work with. They set screed pipes (3/4 inch) at specific pitches (1 inch drop per 8 feet of run) to ensure proper water drainage and a perfectly level, pitched surface, avoiding water pooling. This precise depth for the leveling base is crucial to prevent paver shifting.

Goal: The sub-base is prepared using Class 5 aggregate, with screed pipes set to achieve proper pitch for drainage and a stable foundation for the pavers.

Tools and materials

  • Rakes
  • Screed Pipes (3/4 inch)
  • Shovels
  • Skid Steer Loader
  • Granite Chips
  • Recycled Class 5 Aggregate

What they say

Hide

Sambo's actually right on this point. Um, but here I want to define class 5 just so you guys know. Class 5 is a 3/4 inch rock that has uh all sight all different granular sizes down to fines in it and it packs up. But there's natural stone class 5 and there's recycled class 5. Now, one of the benefits of recycled class 5 that we're using in this video here is the fact that once it's in place and compacts, it turns into pretty much concrete again. I mean, it gives you such a solid foundation, but it is a little more difficult to work with than natural stone class 5. Now, coming up here in just a few moments, you're going to see that we're using screed pipes. And the way we ensure that our patio is completely flat and level, actually tech Oh, nope, nope, nope. Flat and level would be the wrong technical term. We do not want a flat and level patio ever, ever, ever because we don't want water to pull. We want to have one inch of drop per 8 foot of run. So to make sure that we hit that perfect proper pitch, say that fast five times, we use screed pipes. And the screed pipes allow us to get everything dialed straight in all the way across without it having to individually level each block. So, as you watch the next segment of the video and you see these screed pipes in and we're using 3/4 in screed pipes and here that's a critical measurement as well because when you put the screed pipes in, you get your you first you get your base in the right to the right depth that you want and that's always 6 in minimum unless you're putting it under a driveway where you got going to have heavy vehicle traffic. Then you want to go 8 10 or even 12 in deeper. But also, you want to have when you've put your fine layer of sand in or in this case, we're going to be using granite chips. Uh you want to have that dialed directly in because when you put a patio down, if you have too much sand, the patio can shift and move, especially if you're using smaller PA blocks. Now, in this case, we're not using smaller PA blocks, but here's the point I want you to think about. If you have your sand too deep, it doesn't compact as same as the base. So, now you've stratified your base material. You've got your your in this case uh uh 3/4 not 3/4 clear your recycled class 5 and then you have your base material and if we were using sand which a lot of people use which is okay it's appropriate if you have that too much when you put your pavers on top if there's a point of pressure on any one of…