Prepare Site and Position Helical Pile
0:00
0:21
10.4K views
At 0:00 in
GoliathTech is here, you know what that means!!
What happens here
Begin by ensuring the ground at the generator installation site is properly excavated and leveled according to engineering specifications. This creates the initial space for the helical pile. Manually lift and position the helical pile, which is a steel shaft with helical bearing plates, vertically into the center of the excavated spot. Ensure it is as plumb as possible before connecting the driving equipment.
Goal: The initial step involves preparing the installation site, which includes excavating the area to the required depth. Following this, the helical pile is carefully positioned vertically into the ground at the designated location for the foundation.
Tools and materials
- Excavation Tools
- Helical Pile
- Leveling Tool