Soil Engineering Analysis and Footing Recommendations
8:06
15:50
50.6K views
At 8:06 in
FAIL running the Tractor Loader backhoe 4 k video . part 2
What happens here
The soil engineer, Brian, evaluates a soil sample extracted from the test pit. He identifies the soil as having a high silt content and being very moist, which feels 'like sucking on a straw.' He explains that this type of soil is not ideal for foundations. For building footings in such conditions, it would be necessary to over-dig the foundation area by approximately 2 feet (24 inches) and then compact the soil in 1-foot (12-inch) lifts to create a stable base for a standard 20-inch wide footing.
Goal: Assess soil characteristics and determine appropriate foundation requirements