Backfill and Compact Aggregate Behind Wall

10:04
14:14
84.7K views

At 10:04 in

Double Terraced Retaining wall crashes down pt2

What happens here

Once the first course of blocks is laid, or as subsequent courses are added, begin to backfill the area immediately behind the retaining wall with the 3/4 clear aggregate. This material, distinct from 'class 5' which contains fines, allows water to pass freely, preventing hydrostatic pressure. Dump the aggregate in lifts (layers) of approximately 6-8 inches. After spreading each lift with a rake or shovel, thoroughly compact it using the plate compactor. Repeat this process as the wall builds up, ensuring a solid, well-drained fill behind the entire retaining wall structure.

Goal: After installing each course of blocks, backfill the area behind the wall with 3/4 clear aggregate and compact it in lifts to ensure stability and drainage.

Tools and materials

  • Cat Skid Steer Loader
  • Plate Compactor
  • Rake
  • Shovel
  • 3/4 Clear Aggregate

What they say

Hide

[Music] fan places the shovel to mark the center of where you want Lane to dump the draining name with the bottom wall getting close to height they feel comfortable enough to take out the upper wall play it safe and not jeopardize that upper Dhiraj a lot of the removals are done by hand all right so we got drain tile down the class five in up to this point and originally this was a little two-tier wall so there was one here and then obviously one that we've been tearing out but what we're going to do next is start adjusting this great we're going to be shaving it down

Auto-generated from the video audio.