Skip to main content

Site Planning and Charger Design

0:45
2:35
22.7K views

At 0:45 in

Commercial EV Charging Station Installs⚡️ My Dad shows Step-by-Step how to do it, Thoughts?

What happens here

The electrician outlines the site-specific challenges and design changes. Originally, chargers were planned for a grassy area, but this was changed due to residents leaving charging cables on the sidewalk, creating a tripping hazard. The revised plan involves trenching to install dual-headed, shared charging stations along the parking spaces. These ChargePoint stations will be placed every two parking spaces, allowing two cars to share one charging unit. He clarifies that if two cars charge simultaneously, they will split the power feed rather than each receiving a full individual feed.

Goal: Detail the revised installation plan for EV chargers and their operational specifics.

Tools and materials

  • ChargePoint EV Chargers ChargePoint — The specific brand of dual-headed EV charging stations being installed

What they say

Hide

to end up putting EV charging. Originally, we were going to put it in the grass here, but we ran we run into problems with people leaving the cables laying and blocking this sidewalk. All right. So, we're going to end up trenching and we're going to end up putting a charger here and then every other every two parking spaces. So, it's going to be a dual headed shared charging station. Believe it's um a charge point. I I have to say it's going to have two yo-yos to be able to charge. So, it's going to be one feed feeding two of the chargers. Now, if two cars are charging at the same time, they're going to split that. They're not going to get an individual feed. They're going to share the power feed. I'll get to that in a minute. But basically under here is the

Auto-generated from the video audio.