Skip to main content

Final Floor Sheathing and Windows

17:27
23:09
11K views

At 17:27 in

Building The Premier Dream Shop - Part 3

What happens here

Workers continue to install plywood sheets for the subfloor of the second story, ensuring all seams are staggered and each panel is securely fastened to the floor joists with a nail gun. Small cuts are made using a circular saw for precise fitting. After the subfloor is laid, the final pieces of plywood sheathing are installed around the perimeter of the second story. Windows are installed into the openings on the gable ends, marking the completion of the exterior framing and floor system.

Goal: Complete the installation of the remaining subfloor panels on the second story. Ensure proper spacing and nailing. Install windows into designated openings in the gable ends.

Tools and materials

  • Circular Saw
  • Nail Gun
  • Plywood Sheets
  • Tyvek Wrap
  • Windows