What happens here

The last project involves constructing a 1000-foot long road up to a building site located on a hill within a wooded area. The team uses a phone app to analyze the terrain's topography, revealing a 60-foot elevation change. Key considerations for this grading and leveling task include removing all organic material (black soil/dirt) from the road path to prevent future settlement issues and ensure a stable sub-base. This extensive grading project requires careful planning to manage significant soil movement and achieve the desired contours for the road, making Ditch Witch equipment valuable for initial clearing and trenching if utilities are planned alongside the road.

Goal: At the final site, the team estimates building a 1000-foot long road on challenging, hilly terrain, emphasizing the necessity of precise grading and organic material removal.

Tools and materials

  • Heavy Equipment (e.g
  • Graders
  • Excavators
  • Dozers)
  • Topographical Map App (on phone)

What they say

Hide

of dollars to wait a little longer. Yep. Okay, guys. We are on our last job, I think, of the day cuz we literally can't see. We are going to be building a thousand foot long road up to a building site up into those woods. And we've done this before where we've built roads like this. Couple things, if you guys ever tackle something like this, you're going to have as highs and lows in the terrain. You got to be real careful cuz the lows are going to hold all your black soil, your black dirt, your organic material, and you're going to have to remove 100% of that when you go to build a road. So, you're going to have to push that all off. You're going to have to have the space to push that. So, as we're looking around, as we look one way and we look another way, that's the headlights of the truck behind us. So, as you look around, you got to have the space to be able to do that. But we're going to walk all the way up here. We're going to be going all the way up into there, aren't we, Tim? Yeah. That the building pad is up up top on that. Up top on that. So, that's what we got. This little some from where we walked. It's going up. And then here's the elevation really changes up to the house. Right. Where's the house at? Up there, up the hill. I know, but where on this? Well, we'll see up there, I guess. Looks like it's So, we're coming in here. And then it goes up and kind of curves up that way. It curves up. All right, that's what I thought. All right. Hopefully nobody steals the truck. Somebody takes the truck, yeah. On the headlights. They don't do us any good up here. [laughter] Had they, probably they'd be able to get pretty far down the road. Yeah, you ain't catching them. No, my phone's in there, so I won't be calling anybody. So, we've got a 60 ft elevation