What happens here

Using wire cutters, separate the individual service conductors from the main service cable bundle. Carefully pull these conductors through the upper conduit, feeding them into the meter base enclosure. This step requires handling the large gauge wires to avoid kinks or damage.

Goal: Route the main electrical service conductors into the meter base.

Tools and materials

  • Meter Base Eaton — The enclosure where the electrical meter is installed and service conductors terminate
  • Service Conductors — Carrying the main electrical power to the building
  • Wire Cutters/Strippers Milwaukee — Separating the conductors from the main service cable