Skip to main content

Interpreting Bid Tabulation Results

6:29
9:33
42.2K views

At 6:29 in

Bidding and Estimating Stupid Mistakes Landscapers & Contractors Make when pricing their jobs

What happens here

The creator presents the '2018 Farmington Outdoor Pool Demolition Project Bid Tabulation' sheet, showing the mobilization, demolition & removal, granular fill, topsoil, seeding erosion control & site restoration, and total bid for several companies. He points out the two lowest bids in the $50k range and highlights well-established demolition companies like 'Vite and Bolander' whose bids are considerably higher, suggesting their prices are more accurate indicators of real costs.

Goal: Learn to read and interpret bid tabulation sheets to gauge competitive pricing.

Tools and materials

  • Bid Tabulation Sheet N/A — Document showing detailed bids from various contractors